Is the Bay Delta Conservation Plan a Doable Deal?

Part 1: DWR underestimates capital costs of BDCP water facility by $2 billion

Beats me whether the Bay Delta Conservation Plan (“BDCP”) is a doable deal.  My reaction is from a review of the meeting notes and materials posted by Chris Austin in Maven’s Notebook on the July 17th  presentation by the Department of Water Resources.  Ms. Austin has provided an invaluable service of making available detailed meeting notes (in her characteristic factual style) and source documents for her readers.  Whatever one’s view is on the BDCP, all should express their gratitude to Maven.

At this stage, the BDCP is still a “concept deal.” Some concept deals mature into real projects.  Others wither away.  Further refinements in analysis and consideration will determine BDCP’s destiny.  BDCP has problem children:

  • Capital costs: understated
  • Cost of water: obscured
  • Project risks: not transparently addressed
  • The prospect of “New Water Bonds” (to fund conservation of species): overstated
  • The case for economic benefits: not yet compelling

As the BDCP conversation moves from internal deliberations within DWR and its consultants to the water community, water users, public and (most importantly?) capital markets, BDCP proponents will find that they must address fundamental questions more thoroughly (and in some cases correctly).  A prudent person needs more refinements and analysis before making a responsible “go” decision.

My Perspective

This is the first post in a series on the BDCP.  My purpose is not to advocate on behalf or against the BDCP.  Instead, my purpose is to share my perspective on the factual and analytical foundations behind DWR’s project assessment.  As such, I am drawing upon more than three decades of experience in putting together transactions, conducting due diligence on water investments, and managing projects.

From this perspective, I read Chris Austin’s post of meeting notes and materials as an exercise in due diligence.  Imagining myself in a conference room on the top floor of a downtown office building, the “DWR team” walked into the room to “pitch their deal” to a client.  Here are my observations (commensurate with my remuneration?).

Before sharing my “client” report, let me state the limited scope of my review on project costs.  I’m using DWR’s estimates of costs of the myriad of activities in the BDCP.  I am also focusing on the water facility, although all the considerations discussed below may equally apply to mitigation activities and species conservation efforts.  In effect, my client has asked me “can this dog hunt for water users”?  For reasons discussed in my third post in this series, I look at the viability of public funding for conservation of species.

August 13 update:  Based on feedback, I was unclear about the “scenario” of my posts.  Stratecon does not have a client for this analysis.  Instead, I have taken the approach of SUPPOSE I had a client who asked me to conduct a due diligence review.  As such, what would I say?   The discussion and analysis is SOLELY mine.  I apologize for the confusion.  It has always been our policy (for 30 plus years) to disclose whether any issue written about also involves a client.  

How Do the Numbers Work?

As a Ph.D. economist, I’m comfortable with “the lingo”: constant dollars, nominal dollars, discount rates, real interest rates, nominal interest rates, present value and so on.  Below, I focus on the cost of the water conveyance facility that accounts for the bulk of estimated project costs.

Let’s start with the estimated capital cost of the BDCP’s water facility.  DWR estimates the sum of annual construction, design and (construction) permitting costs incurred over the first 10 years of the project at $14.5 billion (2012$) (Table 8-7, Chapter 8).  The estimate is in 2012$; that is, the estimated cost of the project under 2012 market conditions.  The cost estimate reflects historical cost estimates prepared in earlier years adjusted by “various price indices, including consumer price indices . . . and civil works construction cost indices . . .” (section 8.3.3, Chapter 8).

What is the project’s anticipated start date?  Not explicitly stated.  I take a hint that the “first year of the project” is after receipt of permits from federal and state environmental agencies and through the permit term (section 8.3.1).  Diving deep into the background materials, the first project year is evidently 2015 2016 with construction expenditures occurring through 2025 (see Table 8-49, Chapter 8).  A simple declarative sentence would have been appreciated–“assumption: the project starts in the year 2015 2016.”

Assuming that the cost projections are correct, the financial valuation calculates the present value of the capital expenditure schedule.  (Oddly, DWR does not state of the date of its valuation–more below).  Present value takes into account the time value of money.  Since the cost estimates are in 2012$, the calculation uses a “real interest rate” (an interest rate adjusted for inflation).  Based on Department of Interior guidelines, DWR uses a real interest rate of 2.25%.  Assuming an inflation rate of 2.1%, the real interest rate is consistent with a nominal interest rate (interest rate not adjusted by inflation) of 4.375% (approximately).  The discussion at the July 22nd meeting raised issues about interest rate assumptions (see my next post in this series).

Under these assumptions, the present value of capital expenditures on the BDCP water facility is $12.7 billion (2012$) as of (the unstated valuation date of) January 1, 2015 2016.  (I was able to replicate within $7 million DWR’s estimate assuming a January 1, 2015 2016 start date for calculation of present value–the small difference is probably due to rounding of numbers.)

Under the BDCP plan, state and federal water contractors would pay these construction costs, operation costs and mitigation costs.  The present value of operating costs and mitigation costs each equal about 5% of the present value of capital costs.  Therefore, the discussion continues its focus on the bulk of the financial commitment—capital costs.

Capital Costs of Water Facility Understated

DWR excludes three considerations (either by oversight or assumption) that understates the present value of capital costs for the water facility:

  • Increases in real construction costs between 2012 and the construction period (oversight)
  • Mid-year adjustment in the calculation of present value (technical oversight)
  • Cost of finance (by assumption)

As shown below, reasonable accommodation for these considerations increases the estimated present value of capital costs by $1.9 to $2.2 billion.  In other words, federal and state water contractors would have a $14.7 to $14.9 billion obligation to cover on January 1, 2015, not $12.7 billion in inflation-adjusted dollars.

Increases in Real Costs Between 2012 and the End of the Construction Period

As with many water projects, completion of construction is many years after the date of estimated capital costs (2012$).  By concentrating on inflation-adjusted (2012) dollars, DWR correctly removes the effect of inflation.  However, DWR did not consider the impact of changes in the real (inflation-adjusted) cost of construction activities.  Since 2000, for example, the Bureau of Reclamation construction cost indices have increased at an annual rate of 3.7% while the Consumer Price Index increased at an annual rate of 2.6%.  In other words, the real cost of construction activities (as measured by the Bureau’s cost indices) has increased at an annual rate of 1.1%.

Remarkably, DWR does not discuss the trends in cost indices.  Ironically, it updates historic cost estimates to 2012 with adjustment based on cost indices (see above). Based on the Bureau of Reclamation indices, projecting an annual increase of 1.1% in the inflation-adjusted cost through the construction period of the BDCP project increases the present value of water facility construction costs by $1.4, from $12.7 billion to $14.1 billion (see chart).

 BDCP Water Facility Capital Costs

My purpose is not to criticize DWR (their approach is a common one).  Instead, my purpose is to note that perhaps a reason construction projects are almost always more costly than initially estimated is that opinions of probable cost ignore increases in the real cost of construction between the time an opinion of probable cost is prepared and when construction is completed.  Project analysis that ignores the trends in economic conditions misstates project costs.  When real costs are rising, project costs are inevitably understated.  The opposite is also true.

Mid-Year Adjustment

This is a technical issue worth $308 million.  DWR calculates present value evidently assumes that all costs occur year-end.  As a practical matter, cash flows occur throughout the year.  The mid-year adjustment assumes that cash outflows are uniformly distributed throughout the year (consult a finance book for details).  This adjustment is consistent with discussion at the July 17th meeting about taking into account accrued interest when the timing of cash outflows do not match the timing of cash inflows (more on this in my next post in this series).

Cost of Finance

DWR expressly does not develop a finance plan as part of its project assessment.  While this is common practice, this materially understates the cost of BDCP capital investment.  Capital financing is not free.  Underwriting costs alone could be hundred of million of dollars.

Capital financings also have debt service requirements.  For the State Water Project, the debt service reserve is 6 months of the maximum annual debt service payment over the life of bonds.  The debt service requirement on a $14.4 billion capital investment is $409 million for a 40-year bond (DWR loan term) using DWR’s interest rate assumptions.  Water users must either put up this money at financing (a form of equity investment) or increase their borrowing by the amount of the debt reserve (the common practice in municipal finance).

There is good news about debt reserves.  During the term of the financing, short-term interest can be earned (present value of interest earnings is $76 million assuming a 1% return from short-term, low risk instruments).  When the bonds are paid-off, the debt reserve could also be released back to water users.  Assuming that the term of the financing is 40 years, the present value of having $409 million released in 40 years is $72 million.  Therefore, the net cost of the debt reserve is $260 million (rounded).

This estimate of the required debt reserve may be understated.  While DWR puts up a debt reserve of 50% of maximum annual debt service, debt reserves of 100% of maximum annual debt service is more common in municipal finance.  If this were the case for the BDCP water facility, then the net cost of the debt reserve would be $521 million.

In other words, by not developing a finance plan, DWR’s cost analysis is incomplete.  Again, DWR’s approach is common in the industry.  Economics and finance teach that the present value analysis (provided that one chooses the “correct” interest rate) accurately takes into account financing.  The “correct” interest rate includes the interest payment to financiers plus an amortization of financing costs, such as underwriting costs (which are not included in my estimate) and debt reserves (which are included).  Again, more on this in my next post in this series where the reader’s bonus is yet another concept of interest–“true interest cost”.

Altogether Now

The table below collects the adjustments (I show the range of the debt reserve depending on whether a debt reserve involves six months or one-year of maximum annual debt service):

Item

Amount (billion)

DWR Estimate of Present Value of Capital Expenditures

$12.708

Adjustment for Increased Real Costs Through   Construction

  $1.375

Sub-Total

$14.082

Mid-Year Adjustment

 $0.308

Sub-Total

$14.390

Debt Service Reserve
    Size of reserve

$0.409 ($0.817)

    Value of   Earned Interest

-$0.076 (-$0.152)

    Value of release   at end of financing

-$0.057 (-$0.114)

    Net Cost

$0.260 ($0.521)

Grand Total

$14.650 ($14,911)

Conclusion

Economics and finance must be integrated into project cost assessment and DWR’s assessment of the BDCP water facility is no exception.  Actual project costs depend on market conditions when they are built, not years earlier when preliminary cost analyses were prepared. Project financing includes more than interest rates.  Financial reserves must also be committed.  We will see that the finance plan will also have a critical impact on water costs incurred by water users when we discuss debt coverage ratios.

With a $14.7 to $14.9 billion estimated capital cost obligation, what is the cost of water for water users?  See my next post in this series on interest rates, risk premium, risk assessments and the cost of water.